Tuesday May 26, 2009
Analysts: Pahang-Selangor tunnel project sign of improving contract flows
By YVONNE TAN
PETALING JAYA: The construction of the 44.6km tunnel to channel raw water from Pahang to Selangor, which will start on June 1, is a significant signal that contract flows are improving, analysts said. “We think this is a good development and it should trigger the award of contracts for the remaining packages in the entire water transfer project,” AmResearch senior analyst Mak Hoy Ken said. “I think we can all heave a sigh of relief that this part of the project is finally underway. It signals that the current government under the new administration is pro active,” Kenanga head of research Yeonzon Yeow told StarBiz yesterday.
A signing ceremony to formalise the award for the construction of the RM1.3bil tunnel was held yesterday between the parties involved. It was witnessed by Energy, Green Technology and Water Minister Datuk Peter Chin Fah Kui.
The main contractor for this project is a consortium in which Japanese contractors Shimizu Corp and Nishimatsu Construction Co Ltd each has an interest of 30% – a majority of 60% – while IJM Corp Bhd and UEM Builders Bhd have 20% each.
It is understood that every party has seconded the relevant staff to a project management team, which will then manage the project collectively.
The tunnel project, which is aimed at meeting the needs of water consumers in Selangor, Kuala Lumpur and Putrajaya until 2025, is estimated to have an overall cost of about RM3.9bil. The RM1.3bil is the first of four phases in the RM3.9bil tunnel project. Besides the tunnel project, there are other works involved in the entire water transfer project, which is estimated to have a cost of about RM8bil. The remaining contracts have not been awarded but it is understood that interested parties have already been pre-qualified for the remaining work packages. When contacted, a UEM Builders Bhd spokesman said the company was “considering” pursuing the other packages in the entire project but did not elaborate.
Kenanga’s Yeow said yesterday’s signing between the parties would serve as a “benchmark” for other key government projects to be sped up. “It bodes well for the economy because then, domestic spending is able to compensate for weaker export sales which is what the Government intended in the first place to counter a major slowdown in economic growth,” he said.
The bulk of the tunnel project cost will be financed through a loan from the Japan International Corp Agency (JICA) while the rest will be funded by a federal government grant.
Once the tunnel is completed, Selangor would have to pay RM80mil a year to the Pahang government for water.
This is an archive of newsclips on CONSTRUCTION INDUSTRY with a good dose of those on ECONOMY thrown in as well. The contents of this blog are purely archival and do not represent anything on the one who blogs, or any persons, pets, properties, accessories or entities associated with him. The blogger is not responsible for any inaccuracies that may be inherent in the materials.
Showing posts with label Shimizu. Show all posts
Showing posts with label Shimizu. Show all posts
Tuesday, May 26, 2009
Thursday, November 27, 2008
Pahang-Selangor water transfer hangs in balance
KUALA LUMPUR, Nov 27 – The Pahang-Selangor water transfer project hangs in the balance over the question of whether the Malaysian government or Japan has the final say on which consortium is awarded the lucrative contract to bore a 45km tunnel through the Titiwangsa Range. At stake also is a RM2.5 billion soft loan from the Japan Bank for International Cooperation (JBIC).
The Malaysian Insider has learnt that the Cabinet and officials from the Ministry of Energy, Water and Communications are resisting attempts by the Japanese International Cooperation Agency to influence the choice of the successful bidder for the contract. Government officials have been tight-lipped about the behind-the-scenes wrangling but Datuk Joseph Salang Gandum’s comment in Parliament last week gave a hint of the seriousness of the issue.
When asked to give an update on the soft loan from Japan Bank for International Cooperation (JBIC) and the status of the water transfer project, he remarked: “Malaysia is a sovereign country and will not sell its dignity and name…the government already has plans if the money is not channelled to us due to certain reasons.”
Checks show that three bids for the project were received from: Shimizu-Nishimatsu-UEM-IJM; Taisei-HRA Teguh and Kajima Construction. From the start, the government made it clear that tender for the water transfer project should be a benchmark for open tenders in the country. The Ministry of Energy, Water and Communications came up with an international competitive bidding scheme to select a international consultants who would scrutinise the bids. It is understood that two of the bidders submitted conditional bids.
Under the international tender process, any company or party that submits a conditional bid should be disqualified. This is because the price quoted in the conditional bid could change substantially. For example, the lowest bidder for the 45-km tunnel job submitted a conditional bid that was based on a particular rock strength of the tunnel. But independent reports obtained by the government suggest that the rock strength is higher than what the cost estimates are based on.
As such, the government believes that it could be saddled with a variation order of several hundred million ringgit if it awards the contract to the consortium with the lowest bid.
It is in favour of awarding the contract for the project to the company which had submitted the second lowest bid, which was also the only bidder who did not submit a conditional tender.
But JICA is insisting that the contract be awarded to the lowest bidder.
The Malaysian Insider understands that the Cabinet was briefed on the stand off and supports the decision of the Energy, Water and Communications ministry to award the contract to the second bidder.
A government official told The Malaysian Insider: “The terms in the bid documents state clearly that we are not bound to accept the lowest bid but must take into account all factors in the tender. Accepting a conditional bid could be disastrous for the government. Based on our research, there is every chance of a variation order between RM200 million to RM400 million.” It is understood that the difference between the lowest and second bid is RM150 million. JICA has apparently asked the government to negotiate with the party with the lowest tender and get them to remove the “variable component” of the bid.
Government officials believe that going down this path could lead to suits by the two other companies that took part in the tender process. The reason: there is a clause which states that no party can alter, correct or withdraw anything from their bid documents once it has been opened and evaluated.
So the standoff continues. But it is learnt that government officials are willing to forego the Japanese loan. “This is an issue of sovereign rights. Malaysia will be a joke if we have a open tender but don’t follow the rules of the game.” It is unclear how the government plans to raise the RM1.5 billion for the tunnel project if the loan falls through.
The Malaysian Insider has learnt that the Cabinet and officials from the Ministry of Energy, Water and Communications are resisting attempts by the Japanese International Cooperation Agency to influence the choice of the successful bidder for the contract. Government officials have been tight-lipped about the behind-the-scenes wrangling but Datuk Joseph Salang Gandum’s comment in Parliament last week gave a hint of the seriousness of the issue.
When asked to give an update on the soft loan from Japan Bank for International Cooperation (JBIC) and the status of the water transfer project, he remarked: “Malaysia is a sovereign country and will not sell its dignity and name…the government already has plans if the money is not channelled to us due to certain reasons.”
Checks show that three bids for the project were received from: Shimizu-Nishimatsu-UEM-IJM; Taisei-HRA Teguh and Kajima Construction. From the start, the government made it clear that tender for the water transfer project should be a benchmark for open tenders in the country. The Ministry of Energy, Water and Communications came up with an international competitive bidding scheme to select a international consultants who would scrutinise the bids. It is understood that two of the bidders submitted conditional bids.
Under the international tender process, any company or party that submits a conditional bid should be disqualified. This is because the price quoted in the conditional bid could change substantially. For example, the lowest bidder for the 45-km tunnel job submitted a conditional bid that was based on a particular rock strength of the tunnel. But independent reports obtained by the government suggest that the rock strength is higher than what the cost estimates are based on.
As such, the government believes that it could be saddled with a variation order of several hundred million ringgit if it awards the contract to the consortium with the lowest bid.
It is in favour of awarding the contract for the project to the company which had submitted the second lowest bid, which was also the only bidder who did not submit a conditional tender.
But JICA is insisting that the contract be awarded to the lowest bidder.
The Malaysian Insider understands that the Cabinet was briefed on the stand off and supports the decision of the Energy, Water and Communications ministry to award the contract to the second bidder.
A government official told The Malaysian Insider: “The terms in the bid documents state clearly that we are not bound to accept the lowest bid but must take into account all factors in the tender. Accepting a conditional bid could be disastrous for the government. Based on our research, there is every chance of a variation order between RM200 million to RM400 million.” It is understood that the difference between the lowest and second bid is RM150 million. JICA has apparently asked the government to negotiate with the party with the lowest tender and get them to remove the “variable component” of the bid.
Government officials believe that going down this path could lead to suits by the two other companies that took part in the tender process. The reason: there is a clause which states that no party can alter, correct or withdraw anything from their bid documents once it has been opened and evaluated.
So the standoff continues. But it is learnt that government officials are willing to forego the Japanese loan. “This is an issue of sovereign rights. Malaysia will be a joke if we have a open tender but don’t follow the rules of the game.” It is unclear how the government plans to raise the RM1.5 billion for the tunnel project if the loan falls through.
Labels:
HRA Teguh,
IJM,
Kajima,
Nishimatsu,
Pahang Water Tansfer,
Shimizu,
Taisei,
UEM
Friday, August 15, 2008
Interstate water tunnelling
Contractor picked for interstate water tunnelling job
By Ooi Tee Ching
Published: 2008/08/15
BTimes
THE government has decided on the contractor to undertake the 45km tunnelling package of the Pahang-Selangor interstate Raw Water transfer project. The job will be awarded next month.The multi-billion ringgit project involves the construction of the Kelau dam in Pahang and a 44.6km transfer tunnel under the Main Range to bring 2,260 million litres of raw water per day to Hulu Langat treatment plant in Selangor. "The Finance Ministry has approved of the contractor to undertake the tunnelling package," said Energy, Water and Communications Minister Datuk Shaziman Abu Mansor. "We will recommend to JBIC (the Japan Bank for International Co-operation) and the announcement will be made next month," he told reporters after officiating at the opening of the National Solar Photovoltaic conference in Putrajaya yesterday.
In March 2005, the government signed a 82.04 billion yen loan (RM) with JBIC for the project. The loan was to be repaid over 40 years, with an annual interest rate of 0.95 per cent. However, the government can only activate the loan after completing the pre-qualification and tender process. It was reported that three Japanese firms have been shortlisted to carry out the tunnelling package; Shimizu Corp which has UEM group and IJM Corp Bhd as its partners, Taisei Corp (with HRA Teguh Sdn Bhd) and a stand-alone bid by Kajima Corp. Initially slated to commence in 2003, this project was met with protests from both local and international non-governmental organisations like the Centre of Orang Asli Concerns, Sahabat Alam Malaysia and Friends of the Earth-Japan. Due to the protests, the project period had to be revised twice, first to 2005-2012 and then 2008-2015.
By Ooi Tee Ching
Published: 2008/08/15
BTimes
THE government has decided on the contractor to undertake the 45km tunnelling package of the Pahang-Selangor interstate Raw Water transfer project. The job will be awarded next month.The multi-billion ringgit project involves the construction of the Kelau dam in Pahang and a 44.6km transfer tunnel under the Main Range to bring 2,260 million litres of raw water per day to Hulu Langat treatment plant in Selangor. "The Finance Ministry has approved of the contractor to undertake the tunnelling package," said Energy, Water and Communications Minister Datuk Shaziman Abu Mansor. "We will recommend to JBIC (the Japan Bank for International Co-operation) and the announcement will be made next month," he told reporters after officiating at the opening of the National Solar Photovoltaic conference in Putrajaya yesterday.
In March 2005, the government signed a 82.04 billion yen loan (RM) with JBIC for the project. The loan was to be repaid over 40 years, with an annual interest rate of 0.95 per cent. However, the government can only activate the loan after completing the pre-qualification and tender process. It was reported that three Japanese firms have been shortlisted to carry out the tunnelling package; Shimizu Corp which has UEM group and IJM Corp Bhd as its partners, Taisei Corp (with HRA Teguh Sdn Bhd) and a stand-alone bid by Kajima Corp. Initially slated to commence in 2003, this project was met with protests from both local and international non-governmental organisations like the Centre of Orang Asli Concerns, Sahabat Alam Malaysia and Friends of the Earth-Japan. Due to the protests, the project period had to be revised twice, first to 2005-2012 and then 2008-2015.
Subscribe to:
Comments (Atom)
About Me
- burhanlong
- A seeker of success (whatever that means) treading on a path, searching, to return to the wholesomeness that was him when he was launched into this big school called Earth.